钣金、零件 统计时,根据秒数计算计划开始时间
已修改2个文件
11 ■■■■■ 文件已修改
aps-modules/aps-core/src/main/java/com/aps/core/service/impl/ApsPartRouteStatServiceImpl.java 4 ●●●● 补丁 | 查看 | 原始文档 | blame | 历史
aps-modules/aps-core/src/main/java/com/aps/core/service/impl/ApsPlateProcessStatServiceImpl.java 7 ●●●● 补丁 | 查看 | 原始文档 | blame | 历史
aps-modules/aps-core/src/main/java/com/aps/core/service/impl/ApsPartRouteStatServiceImpl.java
@@ -167,8 +167,8 @@
                if (stat.getCurrentProcessNumber().compareTo(stat.getRoadProcessNumber()) < 0) {
                    if (last != null) {
                        LocalDateTime lastStartDate = LocalDateTime.ofInstant(last.getProcessPlanStartDay().toInstant(), ZoneId.systemDefault());
                        long minutes = last.getProcessTotalTime().multiply(new BigDecimal(60)).multiply(new BigDecimal(60)).longValue();
                        LocalDateTime currentStartDate = lastStartDate.plusMinutes(minutes);
                        long seconds = last.getProcessTotalTime().multiply(new BigDecimal(60)).multiply(new BigDecimal(60)).longValue();
                        LocalDateTime currentStartDate = lastStartDate.plusSeconds(seconds);
                        stat.setProcessPlanStartDay(Date.from(currentStartDate.atZone(ZoneId.systemDefault()).toInstant()));
                    }
                }
aps-modules/aps-core/src/main/java/com/aps/core/service/impl/ApsPlateProcessStatServiceImpl.java
@@ -1,5 +1,6 @@
package com.aps.core.service.impl;
import java.math.BigDecimal;
import java.time.*;
import java.util.Date;
import java.util.List;
@@ -137,7 +138,8 @@
                        /*计划完工日=钣金计划工单完成时间*/
                        stat.setProcessPlanEndDay(transDate(orderPlanEndDayLocalDateTime));
                        /*计划开工日=钣金计划工单完成时间 -  工序总工时*/
                        LocalDateTime lastPlanStartDt = orderPlanEndDayLocalDateTime.minusHours(stat.getProcessTotalTime().longValue());
                        long seconds = stat.getProcessTotalTime().multiply(new BigDecimal(60)).multiply(new BigDecimal(60)).longValue();
                        LocalDateTime lastPlanStartDt = orderPlanEndDayLocalDateTime.minusSeconds(seconds);
                        if(lastPlanStartDt.isBefore(now)){
                            hasBefore = true;
                            stat.setProcessPlanStartDay(transDate(now));
@@ -161,7 +163,8 @@
                            /*当前工序结束时间=下一道工序的开始时间*/
                            stat.setProcessPlanEndDay(last.getProcessPlanStartDay());
                            /*开始时间=结束时间-总工时*/
                            LocalDateTime crtStartDt = transLocalDateTime(last.getProcessPlanStartDay()).minusHours(stat.getProcessTotalTime().longValue());
                            long seconds = stat.getProcessTotalTime().multiply(new BigDecimal(60)).multiply(new BigDecimal(60)).longValue();
                            LocalDateTime crtStartDt = transLocalDateTime(last.getProcessPlanStartDay()).minusSeconds(seconds);
                            /*如果开始时间小于当前时间*/
                            if(crtStartDt.isBefore(now)){
                                hasBefore=true;